How is the cost of a CNC part calculated?

Machine hourly rate, labour, material, scrap and outsourcing: how to arrive at the real cost of a part.

How is the cost of a CNC part calculated?
Costing

How is the cost of a CNC part calculated?

Machine hourly rate, labour, material, scrap and outsourcing: how to arrive at the real cost of a part.

Four critical points of the calculation

Click a card to see the screen

Six items, shown separately

Material, machine, labour, outsourcing, scrap and rework stay on separate lines.

Work order cost See the screen

Machine hourly rate helper

Depreciation, energy, maintenance and rent share divided by planned annual hours.

Formula See the screen

Raw duration versus shared duration

Machine cost from raw duration, labour from shared duration; otherwise labour doubles.

Multi-machine work See the screen

Planned versus actual

Both costs sit side by side and the gap appears when the next quotation is priced.

Feedback See the screen
If the cost is wrong, so is the price.

Without a machine hourly rate, machine cost counts as zero and the part looks cheaper than it is.

The six cost items

The real cost of a part is the sum of these:

  • Material: the weighted average cost of the stock issued to the work order
  • Machine: actual machine time multiplied by the machine hourly rate
  • Labour: operator time multiplied by the labour hourly rate
  • Outsourcing: heat treatment, coating, grinding and other subcontracted operations
  • Scrap: the cost of the material and the time lost
  • Rework: work repeated after a nonconformity

The last two must be shown separately. Mixed into the total, the source of the loss is invisible — yet that is the instructive part. If a part consistently runs at eight per cent scrap, the problem is not in the price but in the process.

How is the machine hourly rate found?

In most shops this number has either never been calculated or was worked out once, years ago. The calculation is simple:

Hourly rate = (annual depreciation + energy + maintenance + rent share + other fixed costs) ÷ planned annual running hours

The denominator is not an estimate: it comes from the shift calendar, with breaks and holidays deducted. If maintenance costs are tracked in the system they enter the calculation automatically. Keep an effective date on the rate so that old work orders keep the old rate and past periods stay comparable.

The most common mistake in multi-machine working

If one operator runs two machines at once, the machine cost is calculated from the raw duration — the machine really was busy that long. Labour, however, is calculated from the shared duration, because the person is paid once. Without that distinction labour doubles and the cost table is systematically wrong. In shops where operators run several machines, this single rule decides the accuracy of costing more than anything else.

Planned against actual

The planned cost calculated when the work order is released and the actual cost at the end of the job should sit side by side. The gap tells you which assumption did not hold: did the duration grow, did scrap increase, did the outsourced process cost more than expected? When that gap is in front of you as you price the next quotation, the price rests on your own data rather than on a guess.

One platform, set up for your factory

We listen to how you produce and decide together which modules you need. Installation is done on site and training is included.